Dam Rd. to close in July

July 1, 2025

Dam Rd. to close in July

VASSALBORO – The selectboard has voted to allow the closure of the Dam Rd. due to construction of the Webber Pond dam. The earliest date for bridge closure is Monday, July 15, according to Maine Rivers Project Manager Matt Streeter.

The following are key upcoming dates:

  • Start of construction of Dam Road Extension at McQuarrie Road: Monday, June 30
  • Mobilization of equipment and materials to the dam/fishway location: Monday, July 7
  • Completion of construction of Dam Road Extension at McQuarrie Road: Monday, July 15
  • Earliest date for bridge closure: Monday, July 15

The bridge closure will not continue beyond September 30. Every effort will be made to re-open it sooner. Any questions about the construction schedule may be directed to mstreeter212@gmail.com